13PS.1

 

1. GENERAL RECOMMENDATIONS

In keeping with the ICC’s recommendation, the procedure to be followed for the submission and review of development projects is as follows:

  1. Any project will be submitted in duplicate along with all necessary technical and financial explanatory documents.
  2. The complete file is to be turned over to the General Directorate of the APSARA National Authority.
  3. The General Directorate will forward the file to the Standing Secretariat of the ICC, which will in turn submit it to the group of experts for advisement.
  4. The opinion of the experts is then submitted to the General Directorate of the APSARA National Authority and the ICC Co‑chairman will be briefed.
  5. At the request of the APSARA National Authority, the ICC will examine the file and forward its recommendation to the Chairman of the National Authority.