Restoration of the Srah Srang pier, ANA

In light of the morphological surveys carried out and the pathologies recorded by the team in charge, it is strongly recommended that the team produces without delay a diagnosis as to the causes of these pathologies and designs the final restoration project.To achieve this, it is also recommended to conduct:

A comprehensive analysis of the graphic and photographic documentation from the previous restoration project carried out by EFEO in 1967.

Implementation of geotechnical test pits using a penetrometer to fine tune the design of subsequent foundation works.