Western embankment of Angkor Wat moat (IGeS):

a. Adjust and align the upper part of the steps by replacing, where necessary, the unusable sandstone blocks and by consolidating those that are only partially damaged;

b. Adjust the position and size of the geotextile layer after dismantling of all blocks and replacing the unusable laterite blocks;

c. See to restoration of the visual aspect of the rows of steps between the Italian team work site now underway and APSARA’s work site that will commence shortly;

d. Take into consideration the difference in structure and profile with regard to what may originally have been wooden bridges.