9. Preah Khan Jetty restoration project:

The Ad Hoc group of experts recommends:

9.1. as indicated by the technical index sheet: commencing with carrying out detailed measure drawings of the present condition of the jetty and to mention on a detailed plan the collapsed areas. The analysis of the archaeological layers should yield better understanding of the original structure;

9.2. based on this documentation, a consolidation project of the layers supporting the stepped tiers should be drawn up including the possibility of adding sand to enable resetting missing blocks and also the scattered blocks that may be reused;

This work will help stabilize the jetty platform.

9.3. planning a rainwater drainage system to prevent any decay of the restored structure.